Home » CS takes cognizance of delays in AIIMS Kashmir; Asks to initiate remedial measures to meet November deadline

CS takes cognizance of delays in AIIMS Kashmir; Asks to initiate remedial measures to meet November deadline

SRINAGAR, JUNE 9: Chief Secretary, Atal Dulloo, today chaired a high level meeting to review the progress on the All India Institute of Medical Sciences (AIIMS) project in Kashmir besides addressing the operational and expansion-related issues raised by AIIMS Jammu.

The meeting was attended by Additional Chief Secretary, Jal Shakti Department; Directors of AIIMS Jammu/Kashmir; Divisional Commissioner, Kashmir/Jammu; Secretary, Public Works (R&B); Secretary, Health & Medical Education Department; Project Director, NHAI; Chief Engineers of PHE and PDD and other senior officials.

The Chief Secretary took serious notice of the slow pace of construction work at AIIMS Kashmir and expressed strong dismay over the inadequate deployment of men and machinery on the site. He said that this flagship project, which is being closely monitored at the national level and through the Prime Minister’s PRAGATI review meetings, must not be allowed to lag behind.

He emphasized that accountability must be fixed on the contractor for failing to mobilize sufficient skilled and unskilled labourers to meet the project timelines. He directed the CPWD to expedite the pace of work and initiate the immediate remedial measures on this account. He asked to issue strict instructions to the contractor to avoid any further delay. He categorically stressed that November 2025 deadline must be met without any compromise.

The Chief Secretary assured the executing agencies of full administrative and security support from the local administration to overcome logistical or operational hurdles. He urged all the stakeholders to work in synergy and ensure that on-ground implementation matches the urgency conveyed in official directions.

It was informed during the meeting that around 64% of the project work has been completed, so far. Around 480 workers are currently engaged at the site and this number is expected to rise to 1,500 by the end of June.

It was apprised that in order to start operationalization of this hospital on time procurement and installation of medical equipment is underway. Besides, AIIMS Kashmir is expected to commence its OPD services by April 2026, IPD services by December 2026 and welcome its first batch of MBBS students in July/August 2026, the meeting was apprised.

In addition to the Kashmir project, the Chief Secretary also reviewed pressing issues flagged by the administration of AIIMS Jammu, especially in the context of its future expansion and seamless functioning.

Some of the key requirements discussed included augmentation of water and power supply, construction of an underpass to connect north and south blocks across the National Highway, allotment of additional land for expansion, establishment of a dedicated police post and fire station besides development of a comprehensive drainage system etc.

The Chief Secretary directed the concerned departments to take note of these critical needs and assured the AIIMS Jammu administration of the UT government’s full support in fast-tracking approvals and infrastructural facilitation.

Reiterating the government’s unwavering commitment towards strengthening the tertiary healthcare infrastructure in the Union Territory, Atal Dulloo asked all the departments to work proactively to ensure that both AIIMS campuses evolve into world-class medical institutions. He highlighted that the timely completion and efficient functioning of these institutes is crucial for delivering affordable, accessible and advanced medical care to the citizens of Jammu and Kashmir.

Filed Under: J&K, Latest News Published on June 9, 2025

Primary Sidebar

Latest ePaper

Cover Stories

Champions at Last

Champions at Last

Published on March 4, 2026

How Jammu and Kashmir Conquered the Ranji Trophy and Rewrote Sporting History The afternoon sun baked the red soil of the KSCA Rajnagar Stadium in Hubballi as the final moments of India’s premier domestic cricket competition ticked away. For eight-time champions Karnataka, the fifth and final day was a grueling exercise in inevitability. For the […]

  • Slopes of Unity
  • A Valley Under Diagnosis
  • J&K: North India’s New Medical Hub
  • The Voltage Crisis
  • J&K Budget 2026: J&K Govt Announces Free LPG, Fee Waivers, and Jobs for the Poor
  • Budget Session: LG Unveils Roadmap for a Prosperous J&K
  • 77th Republic Day, J&K Redefines “Integration” Through Rail, Road, and Resolve
  • The Silent Ebb
  • Cloud, Code, and Connectivity
  • Year 2025: How J&K Moved Forward

More Posts from this Category

Education

Redefining Achievement in the Wake of the Winter Session

Published on March 5, 2026

A look back at the January results that shook the Valley, from the record-breaking speed of JKBOSE to the high cost of academic pressure. By Rayees Ahmad Kumar The transition of Jammu and Kashmir’s academic landscape into the 2026 calendar year was marked by a logistical feat that has since become the primary talking point […]

  • A Review of Majeed Masroor’s ‘Faizan-e-Nazar
  • The Dilemma of First Standard Admissions
  • Kashmir’s Pet Boom Demands Responsibility
  • Echoes of the Valley
  • Kupwara Revives Kashmir’s Poetic Tradition

Footer

About Us

Contact Us

e Paper

© 2005–2026 Era Of Kashmir